Government Center

Completed Projects

 

ITB 2022-03 Intersection Improvements at NW 114 Ave & NW 112 Ave on NW 58 St.

  • Project Scope: Intersection Improvements at NW 114 Ave./58 St. and NW 112 Ave./58 St.
  • Estimated Completion Date: April 2023
  • Start Date:  June 20, 2022
  • % Complete: 100%
  • Contractor: H & R Paving
  • Duration: 254 Calendar Days
  • Cost: $296,231.70

 

RFQ 2022- 12 Sidewalk, Curb & Gutter and Miscellaneous Concrete Repair

  • Project Scope: Sidewalk remove and replace (Corsica 2)
  • Estimated Completion Date: May 2023
  • Start Date: March 2023
  • % Complete: 100%
  • Contractor: Miliani Construction Corp.
  • Duration: 30 Calendar Days
  • Cost: $61,146.80
 

 

RFQ 2022- 12 Sidewalk, Curb & Gutter and Miscellaneous Concrete Repair

  • Project Scope: Sidewalk remove and replace (NW 78th Street)
  • Estimated Completion Date: May 2023
  • Start Date: March 2023
  • % Complete: 100%
  • Contractor: Miliani Construction Corp.
  • Duration: 30 Calendar Days
  • Cost: $87,369.70

 

RFQ 2022- 12 Sidewalk, Curb & Gutter and Miscellaneous Concrete Repair

  • Project Scope: Concrete Repair storm structure (1200 NW 78th Avenue)
  • Estimated Completion Date: May 2023
  • Start Date: May 2023
  • % Complete: 100%
  • Contractor: Miliani Construction Corp.
  • Duration: 30 Calendar Days
  • Cost: $5,405.00
 

Current Projects


ITB 2022-05 Doral Boulevard Median Landscaping Improvements

  • Project Scope: Median Landscape Improvements from NW 97th Avenue to Palmetto Expressway
  • Estimated Completion Date: April 2023
  • Start Date: July 25, 2022
  • % Complete: 99%
  • Contractor: Superior Landscaping and Lawn Service, Inc.
  • Duration: 308 Calendar Days
  • Cost: $2,075,404.68


ITB 2022-22 NW 58th Street Outfall

  • Project Scope: Stormwater improvements along NW 57th Street between NW 79th Avenue and NW 78th Avenue and along NW 79th Avenue and NW 58th Street. A 48” Outfall will be constructed along the NW 58th Street canal to discharge near the intersection of NW 79th Avenue and NW 58th Street.  Project also includes Milling & Resurfacing & Stripping.
  • Estimated Completion Date: May 12, 2023
  • Start Date:  November 14, 2022
  • % Complete: 70%
  • Contractor: ADA Engineering Inc.
  • Duration: 180 Calendar Days
  • Cost: $1,576,841.44
  •  Construction Notice - NW 58 Street Outfall
  • CDBG-MIT Requirements: Please refer to the Civil Rights Compliance regulations for the Fair Housing, Equal Employment Opportunity (EEO), and Section 504 and the Americans with Disabilities Act (ADA) as it relates to grant funding. For additional question and/or concerns as it relates to CDBG-MIT grant requirements please contact us 305-593-6740 ext. 6024.
    • Office of Housing Advocacy of Fair Housing Coordinator
       (786) 469-4545
       housingadvocacy@miamidade.gov
       701 NW 1st Court
      Miami, FL 33136
       
    • Miami District Office of EEO Coordination
       1-800-669-4000
       305-808-1758
       100 SE 2nd Street
      Suite 1500
      Miami, FL 33131
       
    • Miami-Dade Office of ADA Coordination
       305-375-5893
       305-375-5753
       111 NW 1st Street
      24th Floor
      Miami, FL 33128


RFQ 2022- 13 Milling, Resurfacing, and Striping Construction Services

  • Project Scope: Milling, Resurfacing, and Striping of various locations-Phase1
  • Estimated Completion Date: June 2023
  • Start Date: May 2023
  • % Complete: 85%
  • Contractor: Weekly Asphalt Paving, Inc.
  • Duration: 30 Calendar Days
  • Cost: $47,223.33

Upcoming Projects


RFQ 2022- 13 Milling, Resurfacing, and Striping Construction Services

  • Project Scope: Milling, Resurfacing, and Striping of various locations-Phase1
  • Estimated Completion Date: June 2023
  • Start Date: June 2023
  • % Complete: 0%
  • Contractor: H&J Asphalt, Inc.
  • Duration: 30 Calendar Days
  • Cost: $17,528.50

RFQ 2022- 13 Milling, Resurfacing, and Striping Construction Services

  • Project Scope: Striping NW 79th Avenue at NW 36th street
  • Estimated Completion Date: June 2023
  • Start Date: June 2023
  • % Complete: 0%
  • Contractor: Weekly Asphalt Paving, Inc.
  • Duration: 30 Calendar Days
  • Cost: $26,650.86
2022 Copyright City of Doral
8401 NW 53rd Terrace Doral, Florida 33166
305-593-6725
Contact Us   |   Job Opportunities   |   Privacy Policy